Features and Limitations of using 2010 Online Editing

Posted By Posted by: EPM Partners on September 11, 2010

Brian posted this link to a new document posted on the Microsoft Project Hompagecontaining a slide deck detailing the limitations of the new 2010 Online Editing feature, I thought that it was definitely worth a mention here as this is one feature that I have had a lot of experience with in 2010.

Here’s a snapshot of the contents:

image

(http://www.microsoft.com/project/en/us/project-server-2010-editions.aspx)

There are a couple of things in there that I had not yet noticed, although the Cost resource one I learnt the hard way trying to save Budget Cost resources in my EPT template!

However a couple of the limitations that have most affected our clients were actually not mentioned, they include:

  • Predecessor / successor links to Summary Tasks – not supported at all.
  • Blank lines – IE lines created in MS Project to space out your schedule.

 

Reposted with permission: Martin Laukkanen