How to Pass a Static Date in Task Type Calculated Field in MS Project

Posted By Posted by: EPM Partners on July 25, 2013

Solution:

Below are the Microsoft Project functions that can be used to pass the static date value in the Task Date type formulae field.

  • ProjDateValue(“10/12/84″))
  • CDate(“10/12/84″))

Note: MS Project 2010 doesn’t accept any year earlier than 1984, however, this issue has been fixed in MS Project 2013.

We hope this quick fix helps you.